Project budget by task report

The Project budget by task report takes one project and shows, for each of its tasks, how far along it is and how its time, cost, and price compare with the estimate. Run it to review a project with its manager, or to spot the tasks that will run over before they do. It reads the estimates on the project's tasks and the time and expenses recorded on them.

Anyone with access to the Reporting tab can run it for a project they have permissions for.

Each task shows its budgeted, worked and remaining figures.

Jump to:

Run the report​

  1. Open the Reporting tab and click 01. Project budget by tasks. In EVX Software's suggested setup, it is under Project Management; your firm may have moved or renamed it.
  2. In Projects, choose the project. The report needs one.
  3. In Group by, choose Tasks or Job phases.
  4. Click Generate report.

Columns​

The first row is the project, with its totals. Each task follows on its own row.

GroupColumnWhat it shows
Percent completedHow far along the task is.
StatusWhether the task is pending or completed.
TimeEstimated (hrs), Worked, Remaining budgetedThe hours estimated, the hours recorded, and the estimated hours left.
CostEstimated cost, Executed cost, Remaining budgetedThe cost estimated, the cost of what was recorded, and what is left of the estimate.
PriceEstimated price, Earned value, Remaining budgetedThe price estimated, the value of the work done so far, and what is left of the estimate.

Use Print, CSV, PDF, or Excel at the top of the report. Close goes back to the filters. See Exports.

Example: a weekly project check​

A project manager runs the report for a cultural resources survey every Friday. All seven tasks show 100% and Completed, worked hours equal the estimates, and earned value equals the estimated price, so the project is ready to close and invoice.

What you can do next​

  1. Budget control report to compare all projects at once.
  2. Important and optional task fields for the estimates and prices the report reads.
  3. Prebuilt reports for the other ready-made reports.