The Budget status report shows, for one or more projects, the time and expenses recorded, what has been invoiced and what hasn't, and how much of the budget is used. It starts with the project's own fields, then lists the labor entry by entry, sums it up by labor category, and ends with the totals and the budget consumption. Use it to check a project before an invoice, a client meeting, or a change order.
Jump to:
Run the report
- Open Reporting and click 02. Project budget status, under 2. Project Management in EVX Software's suggested setup.
- Choose the projects and the options.
- Click Generate report.
For budget, use decides what the budget consumption is measured against.
Filters
| Filter | What it does |
|---|---|
| Projects | The projects to include. |
| For budget, use | What the budget is: None, Sum of budgeted tasks + expenses, or Contract Amount. |
| Include main project information | Prints the project's fields at the top: main data, project information, proposal information, site data, and billing and invoicing information. |
| Include subproject's information | Adds the project's subprojects. |
| Show project's client and start date | Adds the client and the start date. |
| Include invoicing details | Adds the Invoiced and Unbilled columns. |
| Include billing category | Adds the billing category of each entry. |
| Include time entry & expenses description | Adds the description of each time entry and expense. |
| Include estimated time | Adds the estimated time next to the worked time. |
| Include estimated billable | Adds the estimated billable amount. |
| Include open/pending time, Include pending billable | Add the time and amounts still to be worked. |
| Insert page breaks after each project tables | Starts each project on a new page when printed. |
What the report shows
| Section | What it shows |
|---|---|
| Detail of labor | Each time entry: Date, Person, Labor category, Billing rate (hr), Worked time, Worked billable, Invoiced, Unbilled. |
| Summary of labor | The same by labor category, with the estimated time if included, and a Labor subtotal. |
| Totals | Labor total, Expenses total, and Labor and expenses total, with the budget you chose in For budget, use, Budget Consumption as a percentage, and the Contract Type. |
| GRAND TOTALS | The same totals for all the projects in the report. |
Budget Consumption compares what was executed with the budget you chose.
Print or export
Use Print, CSV, PDF, or Excel at the top of the report. Close goes back to the filters. See Exports.
Example: before a change order
A field crew finds more contamination than planned on a former industrial site. Before calling the client, the project manager runs the report with For budget, use set to Contract Amount and Include estimated time ticked. Budget Consumption shows 82 percent used, and the summary shows the field technician's hours already past their estimate. She asks the client for a change order with those numbers.
What you can do next
- Budget control report to compare many projects at once.
- Project budget by task report for one project task by task.
- Project budgets and financial control for how the budget is built.